Office Furniture Project Budget Per Employee: Buyer Guide
Most office furniture budgets blow up not because the desks were overpriced, but because the per-employee number was calculated on the back of a napkin. A real office furniture project budget per employee has to include the workstations, the meeting rooms, the breakout areas, the reception, the storage, the delivery, the installation, and the inevitable surprises. I have seen a £600-per-head plan turn into £1,100 per head once shared spaces and contingency were added. That is a painful conversation with the finance director.

This guide gives you a repeatable method to build a budget per employee that actually holds. It is written from the perspective of someone who has sourced office furniture for corporate projects on both sides of the table — as a buyer and as a supplier. No fluff, just the numbers and the trade-offs.
Why a Simple Desk Cost per Employee Fails
A workstation is the easy part. An ergonomic task chair, a 1400×800mm bench desk, a pedestal, and a monitor arm might land at £450–£650 per person depending on specification and volume. Multiply that by 50 people and you get £22,500–£32,500. That feels like a budget. It is not.
The moment you add a meeting room with a 10-seat table and chairs, a breakout area with soft seating, a reception desk, lockers, and storage, the number climbs fast. Then come the costs that are not furniture at all: delivery, installation, waste removal, and project management. In most office fit-outs I have worked on, the workstation itself accounts for only 40–60% of the total furniture spend.
So the first rule of office furniture project budget per employee is this: start from the whole floor plate, not the desk count.
The Per-Employee Budgeting Method That Works
I use a three-layer approach. It forces you to think about shared spaces as a ratio rather than a guess.
Step 1: Calculate Workstation Cost per Employee
List every item that is assigned to a single person:
- Task chair (specify mechanism and warranty — a £120 chair and a £400 chair are not the same product)
- Desk or bench (fixed, height-adjustable, or sit-stand)
- Pedestal or personal storage
- Monitor arm or stand
- Cable tray and power module
- Any personal locker
Add these up at your chosen specification. For a mid-range corporate spec, I typically see £550–£800 per person. For a high-spec or design-led office, it can exceed £1,200.
Step 2: Add Shared Space as a Percentage
Shared spaces are where budgets quietly die. Rather than cost each meeting room individually, use a ratio based on the total headcount. From projects I have costed, shared-space furniture typically adds 30–50% on top of the workstation total.
A useful breakdown:
| Shared area | Typical share of total furniture budget |
|————-|—————————————-|
| Meeting and collaboration rooms | 15–25% |
| Breakout and soft seating | 8–15% |
| Reception and waiting | 3–8% |
| Storage, lockers, and filing | 5–10% |
If your office is meeting-heavy or client-facing, push toward the upper end. If it is a focused workspace with few visitors, the lower end is realistic.
Step 3: Add Delivery, Installation, and Contingency
This is the layer most buyers forget. On a recent 80-person project, delivery and installation came to 12% of the furniture value. Waste removal and packaging disposal added another 2%. Contingency should be 10–15% of the total — not because you expect problems, but because lead times slip and specifications change.
So the full formula looks like this:
Total office furniture project budget per employee = (workstation cost + shared-space allowance) × (1 + delivery/installation rate) × (1 + contingency rate)
Worked Example: A 25-Person Office
Let’s say you are fitting out a 25-person office in a secondary city. You choose a mid-range specification.
- Workstation cost per person: £600
- Workstation total: 25 × £600 = £15,000
- Shared-space allowance at 35%: £5,250
- Subtotal: £20,250
- Delivery and installation at 10%: £2,025
- Subtotal: £22,275
- Contingency at 12%: £2,673
- Total budget: £24,948
- Budget per employee: £998
That is a realistic all-in figure for a small office. If you had budgeted only the desk cost, you would be nearly £10,000 short.
Worked Example: A 200-Person Office
Scale changes the ratios. Larger projects benefit from volume pricing on workstations, but shared spaces become more complex — more meeting rooms, larger breakout areas, and often a formal reception.
- Workstation cost per person: £550 (volume discount)
- Workstation total: 200 × £550 = £110,000
- Shared-space allowance at 40%: £44,000
- Subtotal: £154,000
- Delivery and installation at 8%: £12,320
- Subtotal: £166,320
- Contingency at 10%: £16,632
- Total budget: £182,952
- Budget per employee: £915
Notice that the per-employee figure is lower than the 25-person office, even though the total is much larger. That is the volume effect. Do not assume a small office gets the same rate.
Phasing the Budget Without Breaking the Project
Not every project needs to be bought in one go. Phasing can help cash flow, but it usually increases the per-unit cost because you lose volume leverage and pay delivery twice.
I recommend phasing only when:
- The headcount will grow by more than 30% within 12 months
- You are refurbishing floor by floor
- Budget approval is split across financial years
If you phase, keep the specification identical across phases. Changing chair models or desk finishes midway creates a mismatched office and complicates warranty support. Also, negotiate the phase-two pricing upfront, even if you order later.
How to Choose an Office Furniture Supplier for Corporate Projects
A supplier who mainly sells to consumers will struggle with a corporate fit-out. You need one who understands project orders, phased deliveries, and site coordination. When you brief an office fit out furniture supplier, ask these questions:
- Can you provide a dedicated project manager for the installation window?
- What is your lead time on the specified chair and desk range, and is it guaranteed?
- Do you handle delivery to floor, assembly, and packaging removal?
- What is the warranty, and who handles claims — you or the manufacturer?
- Can you supply a sample chair and desk finish for sign-off?
A good supplier will also flag specification risks. If you have chosen a chair with a 5-year warranty but your lease is 10 years, they should tell you the long-term cost implication.
Frequently Asked Questions
How do project orders work for office furniture?
A project order is usually a single purchase order covering multiple product lines, delivery phases, and installation services. The supplier assigns a project reference, confirms a delivery schedule, and often holds stock for phased call-offs. You typically pay a deposit at order and the balance on installation or within 30 days. The key difference from a standard order is that changes and lead times are managed through a single point of contact, and the pricing is fixed for the project duration — usually 60–90 days.
What percentage of the furniture budget should contingency be?
For most office fit-outs, 10–15% of the total furniture value is sensible. Go to 15% if the project is fast-track, if you are ordering from overseas, or if the building has access restrictions that could delay installation. Below 10% is risky unless the specification is fully locked and the supplier has confirmed stock.
Is it cheaper to buy office furniture directly from the manufacturer?
Sometimes, but not always. Manufacturers may not offer installation, waste removal, or project management. By the time you add those services, the saving can disappear. For large projects, a supplier who holds manufacturer relationships often gets better total value than going direct, especially on warranty support and delivery coordination.
Getting the Budget Approved
The finance team will not approve a number you cannot defend. Build your office furniture project budget per employee using the three-layer method, show the shared-space ratio and contingency openly, and include one worked example that matches your headcount. If you are comparing suppliers, ask each one to price the same specification so you are comparing like with like. And when you brief an office furniture supplier for corporate projects, share your phasing plan early — it affects their pricing and your total cost per employee.