Most office fit out budgets go wrong in the same place: the furniture line. Not because buyers pick bad products, but because the number they approved at concept stage was built on a per-desk average that never included delivery, install, or the three change orders that landed after the floor plan moved. This office fit out furniture budget planning guide breaks the spend down by workspace type, shows where the hidden costs sit, and explains how to keep change orders from eating your contingency.

I have sat on both sides of this — quoting corporate projects for a supplier and later reviewing budgets for clients — and the pattern is consistent. Projects that budget furniture as a lump sum overrun. Projects that budget it by workspace type, with named allowances for logistics and contingency, land within 5-10%. That gap is worth planning for.
How to Build an Office Fit Out Furniture Budget by Workspace Type
Start with a space schedule, not a catalogue. Walk the floor plan and tag every zone: open workstations, private offices, meeting and huddle rooms, reception, breakout and pantry, focus booths, storage. Each zone has a different cost driver, and averaging them together is how budgets drift.
A rough shape for a mid-market project (say 100-150 desks, mostly hybrid occupancy) looks like this. Treat the ranges as planning anchors, not quotes — specification, finish level and region move them a lot.
| Workspace type | Main cost drivers | Share of furniture budget (typical) |
|—|—|—|
| Open workstations | Desking system, task chairs, screens, power/data | 40-55% |
| Private offices | Desks, ergonomic chairs, storage, guest seating | 10-15% |
| Meeting and huddle rooms | Tables, chairs, AV-ready power, whiteboards | 10-18% |
| Reception and client-facing | Feature desk, lounge seating, side tables | 5-10% |
| Breakout, pantry, soft seating | Lounge chairs, café tables, booth seating | 8-12% |
| Storage and filing | Pedestals, tambours, lockers, archive | 5-8% |
Two things I would flag. First, task chairs are the single line most likely to blow up — ergonomic certification and adjustability push unit cost hard, and buyers often under-spec at budget stage then upgrade later. Second, storage is chronically underestimated in hybrid offices. Fewer desks does not mean less storage; it often means more lockers.
Workstation budgeting: where the money actually goes
For open plan, the desking system (frames, tops, screens, cable trays) usually runs 55-65% of the workstation line, chairs 25-35%, and accessories the rest. If your budget assumes a bench system but the design calls for height-adjustable desks, you are looking at a materially different number. Decide the desking standard before you set the budget, not after.
Meeting rooms: the small-room trap
Huddle rooms are cheap per room and expensive in aggregate. Ten 4-person rooms with tables, chairs and power can rival the cost of forty workstations. Count them honestly.
What Delivery and Installation Really Cost on a Corporate Fit Out
This is the line buyers forget, and it is rarely trivial. For a typical office fit out, delivery and installation commonly land at 8-15% of furniture value, higher for multi-floor sites, after-hours access, or buildings with loading restrictions.
What sits inside that number:
- Freight and delivery — often quoted per drop, not per item. Consolidated deliveries are cheaper but require storage space on site.
- Installation labour — desking systems and task seating are usually included by the supplier; bespoke joinery and AV-integrated tables often are not.
- Lift access and after-hours work — dock bookings, lift protection, and out-of-hours installs add cost in most CBD buildings.
- Packaging removal and waste — cardboard and foam removal is a real line item; some buildings require it.
- Reconfiguration and touch-ups — post-install adjustments after the client walk-through.
Ask for delivery and installation as a separate, itemised line in every quote. When a supplier bundles it into a single “installed price”, you cannot compare bids and you cannot see what a change order will cost you later. A good office furniture supplier for corporate projects will itemise this without being pushed.
Contingency Planning: How Much to Hold Back
My rule of thumb on furniture: hold 8-12% contingency on the furniture subtotal, on top of any project-wide contingency. It feels high until you use it, and you usually use most of it.
Where it gets consumed, based on what I see on real projects:
- Headcount changes during the fit out — the most common cause by far.
- Specification upgrades after ergonomic or acoustic review.
- Power and data changes that force desking reconfiguration.
- Lead-time swaps — paying more for a faster-shipping alternative when a range slips.
- Site conditions — lift dimensions that rule out a table, doorways that force a re-spec.
If you are procuring through an office fit out furniture supplier as a single package, ask explicitly what their contingency assumption is. Some build 5% into their pricing as a buffer; you should not be paying twice for the same protection.
Lead times change your contingency math
Standard desking and seating typically run 6-12 weeks; imported or bespoke items can run 14-20 weeks. If your programme is tight, budget a premium for locally stocked alternatives rather than assuming the lead time will hold. This is where honest suppliers earn their fee.
Avoiding Change-Order Overruns: Six Practical Controls
Change orders are where furniture budgets quietly die. On a badly run project, change orders can add 15-25% to the furniture line. On a well-run one, they stay under 5%. The controls are not complicated.
- Freeze the specification before signing. Sign off seat counts, chair model, desking standard, finish schedule and storage quantities in writing. Verbal approvals are how disputes start.
- Lock unit prices for the project duration. Ask for a price-hold period covering lead time plus install. Commodity pricing moves.
- Agree a change-order rate card upfront. What does an extra desk cost, delivered and installed, mid-project? Get that number in the contract.
- Set a written change threshold. Anything under a defined value can be approved by the project lead; anything above needs sign-off. This stops small requests snowballing.
- Confirm site access before ordering. Lift sizes, door widths, dock booking rules. A table that cannot get into the building is a change order.
- Do a sample install. One workstation and one meeting room set up on site before the bulk delivery catches 80% of issues cheaply.
How project orders work for office furniture
Most corporate orders run as a project order rather than a retail purchase: a formal quotation against a schedule, a deposit (often 30-50%), staged deliveries aligned to the fit out programme, and a retention or final payment after snagging. Ask for the delivery schedule in writing with each stage tied to a floor or zone. Staged delivery protects your cash flow and reduces on-site storage risk.
Where Buyers Commonly Get the Numbers Wrong
A few patterns I see repeatedly, and how to handle them:
- Budgeting per desk when the office is hybrid. If occupancy is 60%, you may genuinely need fewer desks — but more lockers, more focus booths, and better meeting room furniture. Re-allocate rather than cut.
- Forgetting ergonomic compliance. Chairs and desks that meet local DSE requirements cost more. Build that in from the start.
- Ignoring re-use. Refurbishing or re-using existing task chairs and storage can save 10-20% of the furniture line, provided condition is assessed honestly and warranty implications are understood.
- Comparing quotes on headline total only. Compare by workspace type, line by line, with delivery and installation separated. A lower total often hides a thinner specification.
If you are running a competitive tender, send every bidder the same workspace schedule and the same specification standard. It is the only way to compare like with like, and it makes the office fit out furniture supplier conversation far more productive.
A Simple Budget Review Checklist
Before you approve the furniture budget, confirm you have:
- A zone-by-zone schedule with quantities and specification levels
- Task chair and desking standards locked
- Delivery and installation itemised separately, including access constraints
- A stated contingency of 8-12% on furniture, held centrally
- A change-order rate card and approval threshold in the contract
- A staged delivery schedule tied to the fit out programme
- A sample install planned before bulk delivery
None of this is glamorous. But it is the difference between a furniture budget that holds and one that gets renegotiated in the final month of a fit out. If you are briefing an office fit out furniture supplier or running an internal tender, start with the workspace schedule and the contingency policy — the rest of the conversation gets much easier once those two things are on the table.
FAQ
How do project orders work for office furniture?
Typically you receive a formal quotation against your workspace schedule, pay a deposit of around 30-50%, and agree a staged delivery plan aligned to the fit out programme. Final payment is usually released after installation and snagging. Get the schedule, price-hold period and change-order rates in writing before you sign.
What percentage of an office fit out budget should furniture be?
It varies with specification and density, but furniture commonly sits in the region of 15-25% of total fit out cost, with delivery and installation adding 8-15% on top of furniture value. Higher-specification or meeting-room-heavy projects push toward the top of that range.
How do I avoid change-order overruns on an office furniture order?
Freeze the specification and quantities in writing before signing, lock unit prices for the project duration, agree a change-order rate card upfront, and set a written approval threshold for changes. Confirm site access early and run a sample install before the bulk delivery.