We started importing desks for office fit-outs almost by accident. A client had a floor of 140 workstations to furnish in six weeks, and the local dealer quoted a lead time that made the handover date impossible. One container from Foshan later, and we had a new line item in our procurement playbook. Since then, office desk sourcing from China has become routine for us on mid-size commercial fit-outs, but it took a few hard lessons to get the process tight. This is what I’d tell another contractor before they place their first bulk order.

office furniture

The big draw is price, obviously, but the bigger draw is control over specification. When you buy from a dealer, you get what’s on the floor. When you go direct to a factory, you can specify the frame gauge, the edge banding, the cable tray, the exact laminate. For a fit-out where the joinery and the desks have to look like they were designed together, that matters more than the saving.

Start with a spec sheet, not a photo

The single most common mistake I see contractors make is sending a Pinterest photo and asking “how much for this?” You’ll get a price, and it will be wrong, because the factory is guessing at the internals. Fix your specification before you request quotes. At minimum, pin down:

  • Worktop dimensions and thickness, plus the material (melamine-faced chipboard is standard, but check the board grade and the balancing laminate on the underside)
  • Edge banding thickness — 2mm PVC is what I’d insist on for commercial use; 0.8mm looks fine in a sample and chips at the corners within a year
  • Frame type and steel gauge: a 25mm square tube leg frame at 1.5mm wall is a different animal from 1.2mm
  • Cable management: grommets, under-desk trays, vertical risers, and where they sit relative to the power positions in your floor plan
  • Finish reference — a RAL or a laminate code, not “light grey oak”
  • Whether desks are fixed, height-adjustable, or a mix, and if adjustable, the stroke range and motor spec

If you’re also buying task chairs on the same order, it’s worth reading our notes on chair specification before you combine the PO — the QC regime is different and it changes how you schedule inspections.

When you send the RFQ, send it as a drawing or a proper spec table, and ask every factory to quote against the same document. Otherwise you’re comparing apples to a completely different fruit, and the cheapest quote is usually the one that quietly downgraded three things.

Lead times: the number the factory gives you is not the number you plan to

Ask a factory for lead time and they’ll say 25 to 30 days. That’s production time, and it’s often close to true for a straightforward melamine desk. It excludes everything around it.

The realistic chain for a bulk office desk order looks something like this: sample approval (1-2 weeks if you’re decisive, longer if the client keeps changing their mind), deposit and production slot (a few days), production (3-5 weeks depending on volume and how busy their line is), QC inspection (book it a week ahead), packing and trucking to port (3-5 days), sea freight to a European or US port (anywhere from 30 to 45 days depending on route), customs clearance, then inland delivery.

Add it up and you’re typically looking at 10 to 14 weeks door to door. In most cases, that’s fine — fit-out programmes are usually longer. But if your desks are arriving after the flooring goes down and before the snagging walk, you need to work backwards from the handover date, not forwards from the PO.

A few practical things we now do by default:

Book the QC inspection as a fixed milestone in the contract, not an optional extra. A third-party inspection on a 200-desk order costs a fraction of what it costs to receive 200 desks with the wrong grommet position.

Ask for production photos at two points — after frame welding and after packing. It’s a cheap early warning system.

Split the shipment if the programme allows. One container early for the first phase, one later, rather than everything arriving in a single hit with nowhere to store it.

And don’t forget the sample. Approve a physical production sample, keep it on site, and reference it in the PO. “Match the approved sample” sounds vague until there’s a dispute about the laminate colour.

Getting desks into a live building

This is where a China-sourced order diverges from a local one, and it’s the part that catches people out. With a local supplier, delivery and installation are usually bundled. With a factory order, you’re the integrator.

The desks arrive flat-packed or partially assembled, on pallets, shrink-wrapped. Someone has to receive them, check the count against the packing list, move them to the floor, and build them. On a multi-floor fit-out with a goods lift booking window of two hours, that’s a logistics exercise, not a delivery.

What works for us:

Confirm the packing dimensions and pallet weights well in advance, then check them against your lift capacity and door widths. I’ve seen a pallet that wouldn’t go through a stairwell core because nobody measured the turn.

Line up the installation crew before the container lands. If you’re using a separate install team, give them the assembly drawings the factory provides — most will supply them, but ask, because some won’t unless prompted.

Stage by floor, not by container. It sounds obvious, but if pallets are labelled by SKU rather than by room, your installers will spend a day sorting.

Check the hardware kit. Screws, brackets, and cam locks are usually packed per desk or per pallet; confirm which, because a missing bag per desk is a very slow discovery.

If the fit-out includes breakout or meeting furniture — soft seating, booth seating, collaborative tables — the coordination gets more involved, and it’s worth reading our guide to choosing a booth before you lump everything onto one PO with one delivery date.

What to check before you pay the balance

A pre-shipment inspection should cover more than a visual glance. For desks specifically, I’d want to see: worktop flatness and edge banding adhesion, frame weld quality, powder coat coverage on the inside of the legs (a common weak point), a fully assembled sample desk loaded and checked for wobble, and grommet and cable tray alignment against the drawing.

Also confirm the packing method. Corner protection, edge protection, and a moisture barrier are non-negotiable for a six-week sea voyage. Cardboard alone will arrive soft.

One honest caveat: quality varies enormously between factories, and the same factory can vary between orders. The relationship and the inspection discipline matter more than the factory’s showreel. We’ve had excellent results from mid-sized factories that nobody’s heard of and problems from ones with glossy websites.

FAQs

How many desks do I need to order to make importing from China worthwhile?

It depends on the desk and the freight, but in our experience the economics get interesting somewhere around 50 to 80 units, or when the order fills a meaningful share of a container. Below that, the per-unit freight and clearance costs eat the saving. If your fit-out is small, a local dealer is often the smarter call.

Can the factory handle custom sizes to match our joinery?

Usually yes, within reason. Most factories will cut worktops to your dimensions and adjust frame widths, but custom tooling for curved or unusual shapes pushes lead times out and adds cost. Send drawings early and ask directly what’s standard versus bespoke — the answer varies a lot between suppliers.

Who installs the desks once they arrive?

Normally you do, or your fit-out subcontractor does. Some factories can arrange installation through a partner, but I wouldn’t rely on it for a commercial programme. Plan the install as part of your fit-out schedule, with the same labour you’re using for the rest of the furniture, and make sure the assembly instructions arrive with the goods.

Related reading: Become an Office Furniture Distributor: China 101 · Contractor’s Bulk Office Furniture China Sourcing Guide · bulk office desks case: lead times & logistics