Fit-Out Case: Custom Workstation Specs & Lead Times
We took on a 4,200 sq ft office renovation last autumn — a tech client moving into a former law office. The space had good bones: high ceilings, decent light, but a floor plate that was never designed for open-plan workstations. The client wanted 48 custom desks with integrated power, cable management, and a finish that matched the existing walnut millwork. Our first thought was, this is straightforward. Our second thought, three weeks later, was: we should have started the workstation spec before we signed the lease.

That’s the honest takeaway. Custom workstations aren’t hard to buy. They’re hard to sequence. If you’re a fit-out contractor, the workstation package can either glide into the programme or quietly become the thing that pushes handover. Here’s what happened on this job, what we learned, and the specs that actually mattered.
The brief that looked simple (and wasn’t)
The client’s design team gave us a mood board: slim-profile workstations, no visible legs, power and data through the desktop, a walnut veneer that matched the reception desk. They wanted 48 desks in bench runs of six, with a central spine for cable routing. On paper, fine.
The catch was the existing floor. It was a raised access floor with a shallow void — about 65mm clear. Standard bench systems assume you can drop cables straight down and run them under the floor. With that void, we couldn’t use standard floor grommets without cutting into the floor panels and losing structural integrity in the high-traffic zones. So the workstation design had to move the cable path into the desk itself, not under it.
That decision alone changed the lead time. A stock bench with a central spine is a catalogue item. A bench with a custom extruded aluminium spine that carries power and data horizontally, then drops at the end of each run, is a bespoke fabrication. The difference was roughly five weeks versus nine.
Specs that earned their keep
We ended up with a hybrid: a modified standard frame with a custom spine and a locally fabricated walnut veneer top. Here’s what we specified and why, in plain terms.
- Frame: 60mm x 30mm steel box section, powder-coated to RAL 9005. We went with a welded frame rather than knock-down because the client wanted no visible fasteners. Welded frames are heavier and cost more to ship, but they’re stiffer and quieter under load.
- Top: 25mm particleboard core with a 0.6mm walnut veneer, edge-banded in solid walnut. We specified a fire-retardant grade because the building insurer required it for the open-plan zone. That added about 10 days to the veneer lead time.
- Spine: custom 6063 aluminium extrusion, mill finish, with clip-in power modules. We had to tool for the end caps — a one-off cost, but it made the cable entry clean.
- Power: 4x UK socket per two-person bench, plus 2x USB-C PD per person. The client wanted fast charging; we used 65W modules. The power modules were the longest lead item — 7 weeks from order to delivery.
- Cable management: vertical risers at the run ends, with a removable ABS cover. We added a 50mm horizontal tray under the top to keep data cables separate from power.
- Height: fixed at 720mm. The client asked about sit-stand, but the budget didn’t stretch. We offered a retrofit option later; they declined.
One thing I’d flag: the veneer. We matched the reception desk by sending a sample of the existing walnut to the veneer supplier. They came back with a batch that was close but not identical — natural variation. The client signed off on a “blended” look, but if they’d wanted a perfect match we’d have needed to re-veneer the reception desk too. That’s a conversation to have early, not after the desks arrive.
Lead times: where the weeks actually go
Everyone asks for a single lead time. The truth is it’s a stack of lead times, and the longest one isn’t always the one you expect.
On this job, the veneer was 4 weeks, the frames 3 weeks, the power modules 7 weeks, and assembly plus finishing 2 weeks. If we’d ordered everything on day one, the critical path would have been the power modules. But we didn’t. We waited for the client to approve the spine extrusion, which took two weeks of back-and-forth. That pushed the power module order back, and suddenly the whole package was 11 weeks from approval instead of 9.
Here’s the rough sequence we now use for custom workstation packages in fit-outs:
- Design freeze (client sign-off on layout, finish, and power spec). This is the gate. Nothing gets ordered before this.
- Sample approval (veneer and powder coat). Allow 2 weeks if you’re matching existing finishes.
- Long-lead order (power modules, custom extrusions, special veneers). Place this the day after design freeze.
- Frame fabrication (3–4 weeks). Can run in parallel with long-lead items.
- Assembly and finishing (2 weeks).
- Delivery and install (1 week on site, depending on access).
In most cases, the total is 8–12 weeks from design freeze. If you’re dealing with imported power modules or a bespoke veneer match, lean toward 12. If it’s a modified standard product with stock finishes, 8 is realistic.
The mistake we made was treating the power modules as a line item rather than a critical-path item. On the next job, we ordered them as soon as the layout was frozen, even before the client had picked the veneer. The modules are common across finishes, so it was a safe call.
What we’d do differently
Three things stand out.
First, we’d bring the workstation supplier into the pre-construction meeting. We usually involve the M&E contractor and the ceiling guy, but the furniture package often gets left to the end. On this job, the supplier spotted the raised-floor issue in a site walk, but by then we’d already priced the job without the custom spine. That was a variation we didn’t need.
Second, we’d build a mock-up earlier. We assembled one bench in our workshop at week six and the client immediately asked for a deeper cable tray. Better to find that out at week six than on site.
Third, we’d separate the power spec from the furniture spec in the tender. The client changed their mind on USB-C PD late in the day, and because it was bundled with the desks, it triggered a re-quote on the whole package. If power had been a separate line, we could have swapped modules without touching the furniture order.
The handover details that matter
Install was two days for 48 desks, which is about right for pre-assembled benches. The tricky part was the cable pulls. Because the spine carries power and data horizontally, the electrician had to fish cables through the extrusion before we clipped the covers on. We sequenced it: frames in, spine in, electrician pulls and terminates, then tops on. If you put the tops on first, you’re working blind.
We also labelled every power module by desk number and circuit. That sounds obvious, but on a previous job we didn’t, and the client’s IT team spent a day tracing which desk was on which circuit. A roll of numbered labels costs nothing.
FAQs
Can you use stock workstations for a custom look?
Sometimes. If the only custom element is the finish, a stock frame with a custom top is usually the fastest and cheapest route. But if you need a specific cable path, integrated power, or a non-standard size, you’re into fabrication territory. The line is usually drawn by the cable management and power, not the aesthetics.
How early should we order custom workstations in a fit-out programme?
As soon as the layout and power spec are frozen — ideally before you start on site. In our experience, 8–12 weeks from design freeze is realistic for most custom packages. If you leave it until the ceiling grid is going in, you’ll be installing furniture after handover.
What’s the biggest lead-time trap?
Power modules and bespoke veneers. Frames are usually predictable. Power modules, especially if they’re imported or have a specific USB spec, can run 6–8 weeks. And if you’re matching an existing veneer, add two weeks for sampling and approval. Order those first, even if the rest of the spec is still moving.
If you’re planning a fit-out and want to avoid the sequencing mistakes we made, it’s worth reading our guide to choosing a booth for similar project-based lessons, or looking at how we approach commercial renovation planning. The main thing is to treat the workstation package as a critical-path item, not a shopping list.