Fit-out case: China desk lead times & logistics

We had a hard deadline: 14 weeks to fit out a new 1,200 sqm office for a tech client. The catch? They wanted custom-height standing desks with integrated cable management—a spec that local suppliers quoted at nearly double our budget. So we turned to China, as we often do for office furniture. This is what actually happened with lead times and logistics, including the parts that went sideways.

office furniture

Why we went to China (and what we were worried about)

The client’s spec was specific: 120 desks, each with a motorised frame, a bamboo top, and a built-in tray for cables. We’d used European suppliers before, but the lead time was 10–12 weeks and the cost was eye-watering. A contact in Shenzhen had sourced similar desks for another project, so we asked for introductions. Within a week we had three quotes, all 30–40% cheaper than the local option, even after shipping and duties.

The worry, of course, is quality and timing. We’d heard horror stories about container delays and factories that promise the world then miss deadlines. So we built in buffers and planned to inspect before shipping. That decision saved us later.

The timeline that actually worked

Here’s the rough schedule we used. It’s not a template—every project differs—but it gives you a sense of the critical path.

  • Weeks 1–2: Finalise specs, request quotes, negotiate. We settled on a factory in Foshan that specialised in office furniture. They sent samples of the bamboo top and a video of the motor mechanism. We approved after a video call where they demonstrated the desk moving up and down 50 times without a hitch.
  • Week 3: Place order, pay 30% deposit. Production slot confirmed for week 5.
  • Weeks 4–5: Pre-production sample. They sent one complete desk by air (cost about $200, but worth it). We checked the finish and cable tray alignment. Minor issue: the tray was 5mm off-centre. They fixed the jig before mass production.
  • Weeks 6–9: Mass production. We had a third-party inspector visit in week 8 to check 10% of units. They found two desks with slight wobble—the factory adjusted the feet and re-checked all units.
  • Week 10: Goods ready, loaded into a 40ft container. Shipping line booked.
  • Weeks 11–13: Sea freight to Rotterdam (28 days). Then customs clearance and trucking to site.
  • Week 14: Delivery to site, installation by our team. We had a two-day buffer, which we needed because the container arrived a day late due to port congestion.

We cut it fine. In hindsight, 14 weeks is doable but leaves little room for error. If you’re sourcing office desks from China for a fit-out, I’d recommend 16–18 weeks from order to installation unless you’re air-freighting (which rarely makes sense for bulky items).

What we learned about lead times

The factory quoted 45 days for production. That’s typical for custom desks, but it’s calendar days, not working days. Chinese New Year can add two weeks if you’re unlucky—we checked and confirmed the factory would be open. Always ask for a production schedule with milestones.

Shipping is the wild card. We used a freight forwarder who specialises in furniture. They warned us that port congestion in Europe was adding 3–5 days. We factored that in. If you’re planning a fit-out, talk to your forwarder early and get a realistic transit time, not the optimistic one.

One more thing: documentation. The factory sent commercial invoice and packing list, but we had to chase the certificate of origin for customs. It arrived two days before the container loaded. Not ideal. Now we request all docs a week before shipment.

Logistics: from factory to office floor

We chose FOB (free on board) terms, meaning we arranged shipping ourselves. That gave us control but also responsibility. The factory delivered to the port in Shenzhen, and our forwarder handled the rest. For a first-time importer, CIF (cost, insurance, freight) might be simpler—the supplier arranges shipping to your port—but you pay a premium and have less visibility.

The container arrived at our warehouse, not the office, because we needed to assemble and stage the desks. We hired a local crew to unload and assemble. Assembly took two days for 120 desks with two people. The instructions were in Chinese, but the factory sent a video guide after we asked.

Customs was straightforward: we paid duty and VAT, and our forwarder handled the paperwork. But we did get a surprise: the bamboo tops were classified under a different HS code than we expected, which bumped the duty rate slightly. Not a deal-breaker, but worth checking with your customs broker before you order.

The honest verdict

Would we do it again? Yes, for this kind of custom spec. The savings were significant, and the quality was good—the client is happy. But it’s not a set-and-forget process. You need to be hands-on: inspect, communicate, and build in slack. If you’re considering a similar route, our guide to choosing a booth (for trade shows) has some overlapping principles about vetting overseas suppliers. Also, don’t underestimate the time for samples and pre-production checks—they’re your safety net.

For a deeper dive into the sourcing process, see our article on sourcing office furniture from China. And if you’re planning a fit-out, start early and keep a close eye on the calendar.

FAQs

How long does it really take to get desks from China?

From order to delivery, plan for 12–16 weeks. Production takes 6–8 weeks, sea freight 4–6 weeks, plus customs and trucking. Air freight can cut transit to a week but costs 3–4 times more and is rarely worth it for bulky items.

What’s the biggest risk with importing office desks?

Quality issues that you discover after the container arrives. Mitigate with a pre-production sample and a third-party inspection during production. Also, factor in potential delays from port congestion or factory holidays like Chinese New Year.

Should I use FOB or CIF for shipping?

FOB gives you more control and often lower overall cost, but you handle logistics. CIF is simpler—the supplier arranges shipping—but you pay more and have less visibility. For a first shipment, CIF can be less stressful; for repeat orders, FOB is better.