Contractor case: 300 desks from china fit-out

A procurement manager called us on a Tuesday with a problem most fit-out contractors know too well. The lease on their old floor was ending, the new building was handed over late, and they needed roughly 300 workstations landed and installed before the staff moved in. Eleven weeks. The budget ruled out most European brands at that volume. So we did what we’ve done on a few projects now — we sourced the bulk of the office furniture from factories in China and managed the logistics and install ourselves.

office furniture

This is an honest write-up of how that went. Not a sales pitch. There were things that worked well, a couple of things that nearly bit us, and a few decisions I’d change if I were doing it again.

Why we went to China in the first place

Let me be clear about the economics, because it’s the reason anyone does this. On a 300-desk project, the furniture package usually splits into workstations, task chairs, meeting tables, storage, and loose soft seating. For the workstations and storage — the big, heavy, repetitive stuff — Chinese factories quote numbers that are hard to argue with, even after freight and duty. The chairs were a closer call. We ended up splitting the order: chairs from a factory we’d used before, everything else from two suppliers we shortlisted.

The other reason was customisation. The floor plate had a few awkward columns, and we wanted bench desking with a specific cable tray arrangement. The factories we spoke to were comfortable building to a drawing. That flexibility is genuinely useful on a commercial fit-out where nothing is quite standard.

What we did not do is pick the cheapest quote. On a project this size, the cheapest quote is usually the most expensive decision you’ll make.

The sampling stage is where the project is won or lost

We requested samples from four factories. Two sent decent physical samples within about ten days; one sent photos only, which told us nothing about the edge banding or the drawer runners, so we dropped them.

The samples mattered more than the spec sheets. On paper, two suppliers had near-identical melamine board specs. In person, the edge banding on one was noticeably thinner and the laminate had a slight sheen difference to the other. On 300 desks, that sheen difference would have been visible across an entire floor.

A few things I now insist on at sampling:

  • A finished sample of the actual product, not a generic board swatch. Ask for a desktop with the edge banding applied and a drawer unit assembled.
  • The hardware. Get the actual hinges and runners in your hand. This is where cheap builds show themselves.
  • A written confirmation that the production run will match the sample, with the sample retained and referenced in the PO.

We also asked for a video walkthrough of the factory floor. It’s not a substitute for an inspection, but a factory that’s reluctant to show you its line is telling you something.

Getting the drawings and the BOM right

This is the unglamorous part that determines whether the install goes smoothly. We produced a full drawing set — desk layouts, cable management, screen positions, storage configurations — and had the factory confirm each item against a bill of materials before production started.

We caught two errors at this stage. One was a screen height that didn’t match the monitor arms the client had already ordered. The other was a storage unit depth that would have fouled a door swing. Neither was the factory’s fault; both were ours, and both would have been painful to fix after shipping.

If you’re running a project like this, treat the drawing sign-off as a hard gate. Nothing goes into production until the client, the contractor, and the factory have all signed the same document. It feels bureaucratic. It saves you a fortune.

Quality control before anything ships

We used a third-party inspection agency for the pre-shipment check. This is not optional on a 300-desk order. The inspector counted against the BOM, checked board thickness, tested a sample of drawer runners, and photographed everything.

They found a batch of desktops where the laminate had been cut slightly short on one edge. Not catastrophic, but visible. The factory re-ran that batch before loading. If we’d relied on factory photos, those would have shipped.

A practical tip: schedule the inspection with enough float that a re-run is still possible. If your inspection is two days before the vessel sails, you’ve effectively given up your leverage.

Freight, timing, and the bit everyone underestimates

The furniture went by sea freight, consolidated into containers. Sea freight is the sensible choice for volume like this — air freight on desks and storage would have destroyed the budget. The trade-off is time. You’re looking at weeks on the water plus port handling and inland delivery, and that’s before anything is installed.

We built the schedule backwards from the install date and added buffer. Even so, port congestion added a delay we hadn’t planned for. The lesson: on a China-sourced fit-out, the schedule buffer is not padding, it’s part of the plan. If your program has zero float between delivery and handover, this route will stress you.

We also had the goods delivered to a warehouse rather than straight to site, so we could check and stage them before the install crew arrived. On a live building site, a surprise shortage discovered on install day is a very bad day.

What the install actually looked like

Install ran over several days with a crew we’d used before. Because the furniture was flat-packed and modular, the desks went together quickly. The storage took longer than expected — drawer units always do.

The staging decision paid off here. We found a handful of damaged panels from transit, swapped them from the staged stock, and nobody on the client side ever knew. Had those gone straight to site, we’d have been waiting on replacements.

One honest caveat: flat-pack assembly is more labour than a pre-assembled European system. Factor that into your cost comparison. The furniture was cheaper; the install hours were higher. The total still came out ahead, but not by the margin the quote suggested.

The numbers, roughly

I won’t pretend these are precise, because freight and duty move around, but the shape of it is useful:

| Cost area | Rough share of package |

|—|—|

| Furniture ex-works | The bulk of it |

| Sea freight and insurance | Meaningful, scales with volume |

| Duty and clearance | A fixed percentage you should price early |

| Inspection and QC | Small, and worth every penny |

| Install labour | Higher than you’d expect on flat-pack |

Get a customs broker to quote duty before you commit. It’s the number people forget, and it changes the maths.

What I’d do differently

Three things. First, I’d start sampling earlier — we lost about a week waiting on samples that could have been ordered before the design was finalised. Second, I’d push harder for a factory visit or at least a live video call during production, not just at the end. Third, I’d budget more install labour from the outset rather than discovering it mid-project.

If you’re weighing up this route for your own project, our guide to choosing a booth covers some of the same sampling and QC thinking, and the same principles apply to any furniture package.

Would we do it again?

Yes, for a project of this size and profile. The economics work, the factories were responsive, and the quality after inspection was solid. But it’s a managed process, not a transaction. If you’re not prepared to invest in drawings, inspection, and staging, the savings evaporate in rework and delays.

For smaller fit-outs, the freight and inspection overhead starts to outweigh the benefit. That’s a judgement call worth making early.

FAQs

Is it safe to buy office furniture from China for a commercial project?

In most cases, yes, provided you inspect before shipping. The factories we used were competent and built to drawing. The risk isn’t usually capability; it’s the absence of QC. Use a third-party inspector and retain the sample.

How long should I allow from order to installation?

It depends on production time and freight, but I’d plan on several months and build in buffer for port delays. If your program is tight, that’s the main reason to think twice.

Do I need a customs broker?

Practically, yes. Duty, clearance, and documentation are not things to improvise on a large order. Get a quote early so the landed cost is real.